Page 1 of 2

Porjus

Posted: Tue Aug 16, 2022 4:25 pm
by Stese
Again, I've had to abandon a plan, to allow for changing personal circumstances so I'm starting again (3rd iteration!)

I'm following a similar theme as before, basing the area on Central Sweden but in general running whatever I wish... :).

The biggest change to the plan is that rather than a layout outside, I'm now building a modular style layout that I can get out and put away when I need to. Over all, the external area will be 4.8m x 2.4m ( 16' x 4' approx.), made up of 4 x 1.2m*.6m boards, and 6 x 1.2m * .3m boards, arranged in a square. There is an operators space in the middle.

I have a track plan :

Image

The 'missing' section will be a simple loop which will branch into a few lines as a fiddle yard.

The baseboard tops are 9mm ply (I should have got better quality, but oh well), and the bracing is done with 18mm OSB cut into strips.

Image

Image

I've painted them with grey emulsion to tidy them up a bit and have started on track laying... here's the progress so far..

Image

Image

Re: Porjus

Posted: Tue Aug 23, 2022 2:45 pm
by Mountain Goat
Looks good.

Re: Porjus

Posted: Wed Sep 13, 2023 8:38 am
by Stese
It seems my model railway life is all about changes...

In my other thread in layout planning, you'll see that I've abandoned the self build baseboards, and also the circular nature of the layout... in favour of a smaller end-to-end design built on Ikea shelving... I've now got to the point where I can actually start getting track down onto the boards, to test the design of the layout etc...


Image

Image

I've stopped here for now, as I've run out of Insulating Fishplates... but i've got some on the way so there'll be more progress soon! :D

Porjus

Posted: Thu Dec 07, 2023 1:49 pm
by Stese
*Warning picture heavy post!*

Its been a little while since I've posted, but there has been some progress.

I eventually managed to loosely lay all the track, and was happy with the layout and how it looked...

Image Image Image Image
-----

From here, I removed the track, and laid 5mm thick plywood sheets to cover the gaps between the shelves. There's now only 1 gap, and it's bearly 1mm. This has all been painted grey, as a primer and general base colour.

Image Image
-----

Track was then relaid and pinned into place with drawing pins, adding trackfeeds where needed. This allowed to test everything with a free rolling wagon. Holes marked for the location of trackfeeds and points.

There's a few curves in there that weren't quite right, but they were close enough to allow me to move on.

Image Image
-----

Now it was time to lay, glue and paint the cork. Its simply being used to raise the track so a good ballast shoulder can be created. I know painting and ballasting it will prevent it dampening any sound. Holes are drilled for the track & frog feeds, plus larger holes for the point motor pins to come up from the bottom.

Image Image
-----

Now the track is glued into place using normal B&Q PVA. it's held in position using raised thumbtacks.The tacks allow me to place downward pressure on the rail, and also lateral pressure to ensure the desired curves are maintained. This seems to have held well. The track feed wires are passed through the pre-drilled holes, ready for connection underneath.

Image Image Image Image

-----
Turning attention to scenic matters, I've started to layout where physical features will be.

Image Image

Image

-----
Alongside the layout work, I've started the control panel.

Image Image

Image Image

-----

That about brings you up to date... over the christmas break, I'll be putting in all the wiring under the boards, and completing the control panel, so I can start to run trains! woo!

Re: Porjus

Posted: Thu Dec 07, 2023 2:39 pm
by Steve M
Good progress.
But a warning, my wiring started that neatly. ;)

Re: Porjus

Posted: Thu Dec 07, 2023 2:42 pm
by Stese
Oh, i'm not finished in there, I have no doubts it will get messy.

Re: Porjus

Posted: Thu Dec 07, 2023 3:00 pm
by Steve M
The ‘bird’s nest under the boards’ should be seen as a badge of honour. :D

Re: Porjus

Posted: Thu Dec 07, 2023 3:56 pm
by cheshire lines
Looking good so far.

Re: Porjus

Posted: Thu Dec 07, 2023 6:51 pm
by Brian
Wow. A really good start. I like the choice of OSB for the framing. I used 11mm OSB for my "High Hopes" basebaods and aI am very pleased with its strength, flatness and stability. :D The track laying looks good.

Re: Porjus

Posted: Thu Dec 07, 2023 11:10 pm
by bulleidboy
Progressing well - can't wait for the next instalment.